Short answer: yes. Almost every village in Cook, DuPage, Kane and Will counties requires a building permit for a new deck, and most also require one to replace an existing deck. Here is what the process looks like and what inspectors actually check.
1. When you need a permit
Rules vary a little by village, but a permit is almost always required if the deck is attached to the house, more than 30 inches above grade, or larger than about 200 square feet. Replacing boards on an existing frame usually does not need one; replacing the frame or footings does.
- New deck of any size attached to the house
- Any deck more than 30" above the ground
- Replacing the frame, posts or footings
- Adding a roof, pergola or hot tub to a deck
2. What you submit
A typical application includes a plat of survey showing where the deck goes, a framing plan with joist sizes and spans, footing details and a railing and stair detail. Some villages also want a site plan showing setbacks from property lines.

3. How long it takes
| Step | Typical time |
|---|---|
| Drawings and application | 3–5 days |
| Village plan review | 1–4 weeks |
| HOA approval (if any) | 2–6 weeks, often in parallel |
| Inspections during the build | Footing, framing, final |
4. What inspectors check
The footing inspection happens before concrete is poured: depth below the 42" frost line, hole diameter and location. The framing inspection looks at the ledger connection to the house, flashing, joist hangers and beam size. The final checks railings, stairs, guard height and baluster spacing.
“The permit is not a formality. Most of the failing decks we tear out would never have passed a footing or ledger inspection.”
Skipping the permit can come back at you when you sell the house: buyers’ inspectors and title companies increasingly ask for permit records on decks and porches.